Lima 2019 - Advancement of Works


Athletes village

https://www.lima2019.pe/newsletter/avance-de-obras


Main headquarters for accommodation for 7,902 athletes and team officials at the XVIII Pan American Games and Parapan Am Games Lima 2019, which is built to the south of the city of Lima, in the heart of the district of "Villa El Salvador", already counts with the 1096 apartments, which will have the Villa at the end of its construction, finished in structural hull. This construction is in charge of the Besco-Besalco consortium. Of the seven towers that make up the total of the Villa, four of them were completed in advance in structural hull, while the remaining three finished rising in recent days, complying with the schedule that was established for its construction. The official deadline for delivery of the work is February 2019.


The Villa will have 336 apartments for people who have some type of disability and use wheelchairs, during the Parapan Am Games


This has required the construction of wide passages and larger elevators, with capacity for wheelchairs, for the accessibility of the For athletes and officials who will visit us in 2019.


The departments will be 70 m2 and 75 m2, which will have accessible bathrooms for the 2019 Parapan Am Games Lima. There will be 336 departments with these characteristics.


There is also progress in the construction of 3 water cisterns, in which they are built with an excellent rhythm, complying with the schedule established for the works.


At the same time, the foundation and platform works of the basement continue, which will have two levels and which will serve as parking for the legacy.


During the development of Lima 2019, they will be used as areas for warehouses and offices during the Games